News Articles | 26 July 2018
In another exciting project milestone, both TBMs have now left Airport Central Station to tunnel the 2.8km towards Redcliffe Station.
Fact Sheets | 26 June 2018
A number of construction sites have been created along the project’s 8.5 km route and each site has potential noise and vibration sources.
Fact Sheets | 26 June 2018
Before works begin, property condition surveys will be completed on buildings adjacent to construction sites.
News Articles | 15 June 2018
Following TBM Grace’s arrival at Airport Central Station on May 8, TBM Sandy also broke though into the station’s underground box late last month.
Media Statements | 21 May 2018
The two tunnel boring machines for the Forrestfield-Airport Link have now reached Airport Central Station - about a quarter of the way into their 8km journey to Bayswater.