May 2018 update
News Articles | 11 May 2018

May 2018 update

In one of the project's biggest milestones to date, TBM Grace broke through into the underground station box at Airport Central Station on the evening of Tuesday May 8, 2018.

April 2018 update
News Articles | 19 April 2018

April 2018 update

TBM Grace resumed tunnelling this month and has now successfully installed 1034 rings. The restart follows the completion of a comprehensive review into tunnelling operations.

Temporary suspension of tunnelling
Media Statements | 28 March 2018

Temporary suspension of tunnelling

On March 28 the second of the Forrestfield-Airport Link’s two tunnel-boring machines was temporarily halted.

March 2018 update
News Articles | 13 March 2018

March 2018 update

As we progress towards first trains using the Forrestfield Line in 2020, key infrastructure along the new alignment, including all three new stations, is now well into construction.

Tunnelling on track
Media Statements | 19 February 2018

Tunnelling on track

On Sunday 18 February Premier Mark McGowan and Transport Minister Rita Saffioti inspected tunnelling progress, walking the 1km tunnel bored by TBM Sandy